Timetable for the community governance review
We have to complete a community governance review within twelve months from the day on which the council publishes the terms of reference. A community governance review is concluded on the day on which we publish the recommendations made by the community governance review.
Timetable
Action |
Timeline |
Details |
---|---|---|
Report to full council |
Dec 2021 |
Approve the principle of the community governance review and its terms of reference. |
Publish terms of reference |
January 2022 (the CGR must be completed within 12 months of the date of publication) |
Publish terms of reference and notify stakeholders of the commencement of the review. |
Prepare draft consultation document and invite initial submissions |
Feb 2022 to April 2022 (12 weeks) |
Initial submissions invited:
Publish proposals on the LDC website. |
Consider submissions |
May 2022 to July 2022 |
Consider any submissions/representations and prepare report of draft recommendations for full council in July 2022 |
Publish draft recommendations |
July 2022 to September 2022 (10 weeks) |
Publish draft recommendations for further consultation with:
Publish draft recommendations on the LDC website. |
Make final recommendations |
Oct 2022 full council meeting |
Consider any further submissions/representations and prepare final recommendations for report to full council. |
Publish final recommendations |
Dec 2022 |
Publish final recommendations and make order. |